Forfar Restaurant Timeline Alignment

Estate ReviewCoordination Note·Forfar Golf ClubActions Raised

Ancient Links requires a coordinated timeline across asbestos works, kitchen fit-out, restaurant refurbishment, new entrance/pathway works, furniture, staff training, regulatory paperwork and day-one restaurant operations.

Record date
14 Jun 2026
Recorded by
Adair Simpson
Director, Ancient Links
Intelligence source
Desk review
Course
Forfar Golf Club
Angus

Key Observations

Captured findings from the record

  • Issue

    Multiple workstreams are dependent on each other across asbestos, fit-out, furniture, recruitment and regulatory paperwork.

  • Watch

    Kitchen operation and fit-out sequencing may require temporary access arrangements during the works period.

  • Watch

    Furniture decisions affect interior design coordination and must be resolved before procurement.

  • Watch

    Staff recruitment and training are dependent on confirmed build schedule.

  • Issue

    Regulatory paperwork must be submitted in advance of opening day.

Activity History

Chronological record of this intelligence record

  1. 14 Jun 2026 11:20
    Instruction captured via Add Something workflow
    Adair Simpson
  2. 14 Jun 2026 11:20
    Structured into project, decisions, actions, risk and documents
    Estate Intelligence
  3. 14 Jun 2026 11:25
    Assigned as programme lead
    Leanne Mirrey