Viewing as Group GM
Leanne Mirrey
Group General Manager
LM
Programme
Projects
All Course
Forfar Golf Club
Scotscraig Golf Club
Montrose Golf Links
All Status
On Track
Planning
At Risk
Delayed
Complete
All Lead
1Office Technologies
CalForth Construction
Callum Bain
David Brown
John Frulani Architects
Leanne Mirrey
Rosie Anderson
All Phase
Construction
Design
Engineering
Monitoring
Procurement
Strategy
Tender
Showing
12
of 12 projects
Active Projects
12 in scope for your role
Project
Course
Phase
Progress
Due
Lead
Status
Greens & Bunker Reconstruction — Holes 4 to 9
Forfar Golf Club
Construction
62%
Aug 2026
CalForth Construction
On Track
Clubhouse Roof Replacement & Slate Renewal
Forfar Golf Club
Design
22%
Mar 2027
John Frulani Architects
Planning
Estate Irrigation System Replacement
Montrose Golf Links
Procurement
35%
May 2027
CalForth Construction
On Track
Course Drainage Improvement Programme
Scotscraig Golf Club
Construction
41%
Oct 2026
CalForth Construction
At Risk
Heather Regeneration & Ecology Trial
Scotscraig Golf Club
Monitoring
88%
Oct 2026
Callum Bain
On Track
Coastal Erosion Defence — Holes 2 to 5
Montrose Golf Links
Engineering
55%
Apr 2027
CalForth Construction
On Track
Clubhouse Kitchen Refurbishment
Montrose Golf Links
Design
15%
Feb 2027
Rosie Anderson
Planning
Catering & Bar Operator Re-tender
Forfar Golf Club
Tender
50%
Sep 2026
David Brown
On Track
2027 Membership Pricing Review
Scotscraig Golf Club
Strategy
70%
Jul 2026
David Brown
On Track
EV Charging Installation — Visitor Car Park
Montrose Golf Links
Design
25%
Jan 2027
1Office Technologies
Planning
Staff Accommodation Refurbishment — Tay Cottages
Scotscraig Golf Club
Design
30%
Apr 2027
CalForth Construction
Planning
Three-Year Capital Investment Programme 2027–29
Forfar Golf Club
Strategy
45%
Nov 2026
Leanne Mirrey
Planning