Extend primary drainage on the heaviest-clay holes at Scotscraig to reduce winter closures and protect green-fee income.
Phase 1 reduced winter closures by 38% on the front nine. Phase 2 covers fairways 11–15 and is expected to deliver a comparable uplift, paying back lost green-fee income within two seasons.
Construction-ready. Awaiting £280k phase 2 funding release (d3). Programme is at 41% but flagged At Risk pending board funding.
Phase 2 funding release — 30 Jun 2026
Linked Decisions (1)
Decisions raised, under review or approved against this project
Linked Risks (1)
Risks recorded against this project
Linked Actions (1)
Open and recently closed actions
- HighCirculate drainage phase 2 cost plan to directorsEilidh Sinclair · Due Next Mon
Related Estate Intelligence (2)
Walk rounds, building reviews and estate observations referencing this project
Activity Timeline
Decisions, documents, approvals, risks and actions on this project
- Phase 2 funding release raised (d3)Decision · Callum Bain · 08 Jun 2026
- Drainage Phase 2 Cost Plan issuedDocument · Grant Handforth · 07 Jun 2026
- Eilidh Sinclair approved as GMApproval · Eilidh Sinclair · 08 Jun 2026
- Hole 13 standing water photos addedPhoto · Callum Bain · 05 Jun 2026
Stakeholders
Across Ancient Links, CalForth and John Frulani Architects
- CBCallum BainHead Greenkeeper, Scotscraig · Scotscraig Golf Club
- ESEilidh SinclairGeneral Manager, Scotscraig · Scotscraig Golf Club
- GHGrant HandforthDirector & Contracts Manager · CalForth Construction
- DMDavid MirreyProject Manager · CalForth Construction
- LMLeanne MirreyGroup General Manager · Ancient Links
- APArchie PatonDirector · Ancient Links
Linked Documents (1)
- Drainage Phase 2 — Cost Plan & Programmev1.4