Install twelve EV charging bays in the Montrose visitor car park to meet member demand and generate a new tariff revenue line.
Member survey showed 31% own or intend to own an EV within 24 months. 1Office Technologies scoped the integration; CalForth returned turnkey civils and grid upgrade.
Design 25% complete. OZEV grant in preparation; grid capacity assessment with SSEN. Awaiting board approval (d8) on full 12-bay scheme.
Board approval on full scheme — 01 Jul 2026
Linked Decisions (1)
Decisions raised, under review or approved against this project
Linked Risks (1)
Risks recorded against this project
Linked Actions (1)
Open and recently closed actions
- MediumSubmit OZEV grant application — EV baysIain Buchanan · Due 26 Jun
Related Estate Intelligence (1)
Walk rounds, building reviews and estate observations referencing this project
Activity Timeline
Decisions, documents, approvals, risks and actions on this project
- EV charging installation raised (d8)Decision · Iain Buchanan · 30 May 2026
- Angus Energy Proposal v1.2 issuedDocument · Gus Laing · 29 May 2026
- Grid capacity constraint risk added (r9)Risk · Iain Buchanan · 30 May 2026
Stakeholders
Across Ancient Links, CalForth and John Frulani Architects
- IBIain BuchananGeneral Manager, Montrose · Montrose Golf Links
- GHGrant HandforthDirector & Contracts Manager · CalForth Construction
- LMLeanne MirreyGroup General Manager · Ancient Links
- APArchie PatonDirector · Ancient Links
Linked Documents (1)
- EV Charging — Angus Energy Proposalv1.2