Joint review with 1Office Technologies covering grid supply, bay layout and visitor wayfinding. Existing supply will accommodate six bays without upgrade; the full twelve-bay scheme requires an SSEN grid uplift.
Record date
30 May 2026
Recorded by
Iain Buchanan
General Manager, Montrose
Intelligence source
Site survey
Course
Montrose Golf Links
Angus
Key Observations
Captured findings from the record
- Note
Existing supply — confirmed sufficient for six 7kW bays without uplift.
- Watch
Phase 2 (twelve bays) — SSEN uplift quoted at c.£45k; budgetary impact to be reflected in capital plan.
- Issue
Wayfinding — proposed bay layout conflicts with the buggy-shed access route; design to be revised.
Activity History
Chronological record of this intelligence record
- 30 May 2026 10:00Walk-over with 1Office TechnologiesIain Buchanan
- 30 May 2026 17:20Record logged with risk r9 linkedIain Buchanan