Forfar Golf Club · Programme

Forfar Restaurant Opening Programme

Project Summary

Headline status and ownership

Project
Forfar Restaurant Opening Programme
Project Lead
Leanne Mirrey
Status
At Risk
Phase
Planning / Coordination
Start Date
June 2026
Target Completion
May 2027
Progress
12%

Overview

Purpose, background and current position

Purpose

A coordinated programme to align asbestos works, kitchen fit-out, restaurant refurbishment, furniture procurement, recruitment, staff training, regulatory approvals and day-one opening operations for the Forfar restaurant.

Background

Multiple workstreams across asbestos removal, fit-out, furniture, staffing and regulatory approvals are interdependent. Captured via the Add Something workflow on 14 June 2026 from an instruction by Adair Simpson, and structured by Estate Intelligence into a single opening programme.

Current Position

Programme initiated in Planning / Coordination phase. Two decisions raised (d11 temporary kitchen access; d12 layout & furniture). Six actions issued to named owners across asbestos, fit-out, layout, recruitment, events and regulatory paperwork. Status At Risk pending decisions.

Next Key Milestone

Temporary kitchen access decision (d11) — 30 Jun 2026

Linked Decisions (2)

Decisions raised, under review or approved against this project

Linked Risks (1)

Risks recorded against this project

Risk register

Linked Actions (6)

Open and recently closed actions

  • Confirm asbestos removal programme and interface with restaurant fit-out
    Grant Handforth · Due 27 Jun
    High
  • Issue updated restaurant layout including furniture positions
    Rosie Anderson · Due 28 Jun
    High
  • Confirm kitchen fit-out start date and duration
    David Mirrey · Due 30 Jun
    High
  • Prepare staff recruitment and training schedule
    Alex Fairlie · Due 10 Jul
    Medium
  • Confirm list of club events requiring catering during March, April and May
    Fraser Davidson · Due 12 Jul
    Medium
  • Confirm regulatory paperwork requirements and submission dates
    Leanne Mirrey · Due 15 Jul
    High

Related Estate Intelligence (1)

Walk rounds, building reviews and estate observations referencing this project

Activity Timeline

Decisions, documents, approvals, risks and actions on this project

  1. Instruction captured via Add Something workflow
    Note · Adair Simpson · 14 Jun 2026
  2. Temporary kitchen access arrangement raised (d11)
    Decision · Leanne Mirrey · 14 Jun 2026
  3. Final restaurant layout and furniture coordination raised (d12)
    Decision · Rosie Anderson · 14 Jun 2026
  4. Opening delay risk added (r13)
    Risk · Leanne Mirrey · 14 Jun 2026
  5. Restaurant Layout Plan Rev A issued
    Document · Rosie Anderson · 14 Jun 2026
  6. Kitchen Fit-Out Programme v0.3 issued
    Document · David Mirrey · 14 Jun 2026
  7. Opening Readiness Plan (Draft) issued
    Document · Leanne Mirrey · 14 Jun 2026
  8. Staff Recruitment & Training Plan (Draft) issued
    Document · Alex Fairlie · 14 Jun 2026

Stakeholders

Across Ancient Links, CalForth and John Frulani Architects

  • LM
    Leanne Mirrey
    Group General Manager · Ancient Links
  • AS
    Adair Simpson
    Director · Ancient Links
  • GH
    Grant Handforth
    Director & Contracts Manager · CalForth Construction
  • DM
    David Mirrey
    Project Manager · CalForth Construction
  • JF
    John Frulani
    Architect & Owner · John Frulani Architects
  • RA
    Rosie Anderson
    Interior Designer & Associate · John Frulani Architects
  • DB
    David Brown
    Sales Manager · Ancient Links
  • AF
    Alex Fairlie
    HR Manager · Ancient Links
  • FD
    Fraser Davidson
    General Manager, Forfar · Forfar Golf Club

Linked Documents (4)

  • Forfar Restaurant — Layout PlanRev A
  • Forfar Restaurant — Kitchen Fit-Out Programmev0.3
  • Forfar Restaurant — Opening Readiness PlanDraft
  • Forfar Restaurant — Staff Recruitment & Training PlanDraft

Site Records

Photos, intelligence records and surveys

No site records yet.