Mobilisation survey of all four cottages ahead of phase 1 refurbishment. Two cottages (EPC F) require fabric-first upgrades; cottage 3 interim insulation works are holding well; one safety observation on the external stair.
Record date
02 Jun 2026
Recorded by
Grant Handforth
Director & Contracts Manager, CalForth Construction
Intelligence source
Site survey
Course
Scotscraig Golf Club
Fife
Key Observations
Captured findings from the record
- Watch
Cottage 1 & 2 — solid-wall construction; internal wall insulation to specification confirmed feasible.
- Note
Cottage 3 — interim loft insulation in good condition; programme can leave until phase 2.
- Issue
Cottage 4 — external timber stair handrail loose; immediate temporary fix put in place.
Activity History
Chronological record of this intelligence record
- 02 Jun 2026 09:30Mobilisation survey carried out with David MirreyGrant Handforth
- 02 Jun 2026 16:00Record loggedDavid Mirrey
- 03 Jun 2026 08:45Temporary handrail fix verifiedEilidh Sinclair