Executive Summary
Prepared by Leanne Mirrey, Group General Manager
The estate enters the second half of 2026 in measured health. Across Forfar, Scotscraig and Montrose, twelve projects are in flight against the agreed capital plan, with member-facing disruption tracking below the 2025 benchmark. Two programmes — Scotscraig drainage phase 2 and the Forfar clubhouse roof renewal — are pending director sign-off and are the principal items on this board's agenda.
Commercial performance remains ahead of plan. The 2027 membership repricing modelling, the catering re-tender at Forfar and the Montrose kitchen refurbishment together represent the most significant uplift in commercial income for the three-year horizon. The directors are asked to note that 5 risks are currently graded High, of which three have mitigations awaiting board release.
The three-year capital programme draft (£8.4m) is included for first-read endorsement and remains within debt covenant headroom under the modelled inflation scenarios.
Estate Health Dashboard
Headline indicators across the portfolio
High Severity Risks
5 requiring director attention
- HighAccelerated coastal erosion, holes 2–5Montrose Golf Links · Iain Buchanan · Course & Grounds
- HighIrrigation system end-of-life failure riskMontrose Golf Links · Ross McLeod · Course & Grounds
- HighClubhouse roof water ingressForfar Golf Club · Fraser Davidson · Clubhouse & Buildings
- HighCapital programme affordability vs covenant headroomForfar Golf Club · Leanne Mirrey · Governance & Heritage
- HighRestaurant opening delayed due to misaligned workstreamsForfar Golf Club · Leanne Mirrey · Commercial & Hospitality
Decisions Awaiting Approval
11 routed to the board / GM
- Awaiting ApprovalApprove revised bunker reconstruction phasing, holes 4–6Forfar Golf Club · Hamish MacGregor · 12 Jun 2026
- Under ReviewEstate-wide irrigation system replacement — preferred supplierMontrose Golf Links · Ross McLeod · 10 Jun 2026
- Awaiting ApprovalDrainage improvement programme — phase 2 funding releaseScotscraig Golf Club · Callum Bain · 08 Jun 2026
- Awaiting ApprovalClubhouse roof replacement — appointment of slating contractorForfar Golf Club · John Frulani · 06 Jun 2026
- Under ReviewClubhouse kitchen refurbishment — concept design sign-offMontrose Golf Links · Rosie Anderson · 04 Jun 2026
- Awaiting Approval2027 membership pricing strategy & joining feeScotscraig Golf Club · David Brown · 03 Jun 2026
- Under ReviewCatering & bar operator — preferred tender selectionForfar Golf Club · Leanne Mirrey · 01 Jun 2026
- Awaiting ApprovalEV charging installation — visitor car park, twelve baysMontrose Golf Links · Iain Buchanan · 30 May 2026
- Under ReviewThree-year capital investment programme 2027–29Forfar Golf Club · Leanne Mirrey · 22 May 2026
- Awaiting ApprovalTemporary kitchen access arrangement during restaurant worksForfar Golf Club · Leanne Mirrey · 14 Jun 2026
- Under ReviewFinal restaurant layout and furniture coordinationForfar Golf Club · Rosie Anderson · 14 Jun 2026
Projects At Risk
2 requiring intervention or oversight
Open Actions by Priority
16 open across estate teams
- Issue RFI on green 6 sub-base specForfar Golf Club · Hamish MacGregor · Due Tomorrow
- Confirm CalForth Construction phasing scheduleMontrose Golf Links · David Mirrey · Due Fri
- Circulate drainage phase 2 cost plan to directorsScotscraig Golf Club · Eilidh Sinclair · Due Next Mon
- Confirm conservation officer site visit — clubhouse roofForfar Golf Club · Blair Smith · Due 18 Jun
- Draft member communication for 2027 pricingScotscraig Golf Club · Jo Eismont · Due 24 Jun
- Prepare member consultation pack — 3yr capital programmeForfar Golf Club · Jo Eismont · Due 10 Jul
- Confirm asbestos removal programme and interface with restaurant fit-outForfar Golf Club · Grant Handforth · Due 27 Jun
- Issue updated restaurant layout including furniture positionsForfar Golf Club · Rosie Anderson · Due 28 Jun
- Confirm kitchen fit-out start date and durationForfar Golf Club · David Mirrey · Due 30 Jun
- Confirm regulatory paperwork requirements and submission datesForfar Golf Club · Leanne Mirrey · Due 15 Jul
- Circulate coastal-defence tender shortlistMontrose Golf Links · Iain Buchanan · Due Today
- Issue kitchen concept pack to David BrownMontrose Golf Links · Rosie Anderson · Due 20 Jun
- Reference-check Glenisla Hospitality (final two referees)Forfar Golf Club · Alex Fairlie · Due 19 Jun
- Submit OZEV grant application — EV baysMontrose Golf Links · Iain Buchanan · Due 26 Jun
- Prepare staff recruitment and training scheduleForfar Golf Club · Alex Fairlie · Due 10 Jul
- Confirm list of club events requiring catering during March, April and MayForfar Golf Club · Fraser Davidson · Due 12 Jul
Capital Investment Overview
Three-year programme 2027–29 · draft envelope £8.4m
Recent Activity Across The Estate
Latest entries from decisions, documents, photos and actions
- Clubhouse roof method statement issuedDocument · John Frulani · Forfar Golf Club · 11 Jun 2026
- Bunker phasing raised for approvalDecision · Hamish MacGregor · Forfar Golf Club · 12 Jun 2026
- Catering operator tender raisedDecision · Leanne Mirrey · Forfar Golf Club · 01 Jun 2026
- Member consultation pack drafted — 3yr capital programmeAction · Jo Eismont · Forfar Golf Club · 10 Jun 2026
- Tay Cottages refurbishment approvedDecision · Mike Wells · Scotscraig Golf Club · 26 May 2026
- 2027 membership pricing strategy raisedDecision · David Brown · Scotscraig Golf Club · 03 Jun 2026
- Drainage phase 2 cost plan issuedDocument · Grant Handforth · Scotscraig Golf Club · 07 Jun 2026
- Irrigation replacement — preferred tender raisedDecision · Ross McLeod · Montrose Golf Links · 10 Jun 2026
- EV charging installation raisedDecision · Iain Buchanan · Montrose Golf Links · 30 May 2026
- Kitchen refurbishment concept raisedDecision · Rosie Anderson · Montrose Golf Links · 04 Jun 2026